Krondorf Valley Bridge

Construction period

July 26, 2022 – August 19, 2022

Client

Eiffage Infra Süd

Brief description:

  • Installation of 2 pairs of HEB 1000 girders using 2 wire rope hoists, each with a lifting capacity of 300 metric tons
  • Lifting the advance scaffold to dismantle the support towers
  • Lowering the advance scaffold; height approx. 35 m, weight approx. 700 metric tons

Special features:

  • Confined space conditions
  • Installation of the 28-metric-ton wire rope hoist structure on 37-meter-high piers using a 250-metric-ton truck-mounted crane
  • Placing the scaffold on the transverse transfer track