Renovation of the Former Zeuna-Stärker Site in Augsburg
Construction period
July 2023 through April 2024
Client
SOLIDAS Projektentwicklung GmbH
86368 Gersthofen
86368 Gersthofen
Brief Description
- Remediation of zinc contamination using replacement drilling (approx. 4,000 m³ at 209 drilling points)
- Deep compaction using vibro-compaction columns; repeated water exchange from boreholes
- Soil replacement through surface removal and slide rail shoring (approx. 9,500 m³)
Scope and Special Features
- Establishment of a restricted access zone around the existing damaged area, including the installation of a temporary tire-washing station.
- Continuous monitoring by explosive ordnance survey and archaeological teams throughout the entire construction period
- Protection of groundwater outflow via diversion wells
- Close monitoring of potential environmental impacts during construction (vibration, noise, dust, and groundwater monitoring)
- Feeding groundwater from a replacement well into a water treatment plant