Surface Sealing of the Ringgenbach Landfill

Facts and Figures

Construction period

May 2012 – April 2013

Client

Landratsamt Sigmaringen
Leopoldstraße 4
72488 Sigmaringen

Contract Amount

approx. 1,700,000.00 €

Brief description:

  • Approx. 10,000 m³ of waste relocation and installation in accordance with the slope profile
  • Approx. 38,000 m² of surface grading
  • Approx. 25,000 m² of asphalt waterproofing installation
  • Approx. 12,500 m² of waterproofing installation using BAM-approved plastic waterproofing membrane (KDB 2.5 mm)
  • Approx. 25,000 m³ of surface reclamation
  • Approx. 11,500 m³ delivery and installation of FSS material graded to DKI
  • Approx. 12,000 m³ delivery and installation of profiling material loaded to DKI
  • Construction of a concrete structure for surface water collection, approx. 120 m³ UBR
  • Construction of a concrete structure to cross the access road with a rough-bed foundation, approx. 20 m³ UBR
  • Approx. 2,100 m² floor area; construction of strip and individual foundations for the hall of the future wood processing plant