Kornwestheim: Gumpenbach Bridge on the B27
Construction period
March 2, 2022 – March 10, 2022
Client
Wolff und Müller Ingenieurbau GmbH
Brief description:
- Lifting of the semi-integral eastern span of the Gumpenbach Bridge, weighing 4,400 metric tons, using the FLUIDTS lifting system over a distance of 10.55 meters
- Bridge spans: 30 m – 40 m – 30 m
- Translation along 2 abutment axes on the supporting scaffold and along 2 pier axes
Special features:
Use of the FLUIDT transport system consisting of:
- 26 load modules rated at 2,500 kN
- 2 hydraulic power packs for lifting/lowering and 3 hydraulic power packs
for translation - 6 steel guide rails each, measuring 9x1.4 m and 9x1.56 m
- Various steel plates and height adapters
- Nitrogen distribution for all 4 axes
- 1 tool and spare parts container