Bridge over the A7 ST2021 between Finningen and Holzheim
Construction period
14 days
Client
Josef Hebel Construction Company
Riedbachstraße 9
87700 Memmingen
Germany
Riedbachstraße 9
87700 Memmingen
Germany
Construction Work
Demolition of the ST2021 county road bridge over the A7 interstate highway between Holzheim and Finningen
Scope and Special Features
- Installation of 1,000 m² of road protection
- Use of 4 demolition excavators with an operating weight of up to 75 metric tons
- Demolition of the bridge during a 10-hour full closure of the A7 at night
- Demolition of the bridge abutments during an 8-hour full closure of the A7 at night
- Demolition and disposal of 20 metric tons of asbestos-containing waterproofing beneath the bridge caps
- Disposal and removal of all demolition debris
- Demolition of 750 m³ of bridge concrete