B43 Bridge Over DB Facilities in Hanau
Construction period
4 months
Client
Leonhard Weiss GmbH & Co. KG
Wilhelm-Frank-Straße 61
97980 Bad Mergentheim
Germany
Wilhelm-Frank-Straße 61
97980 Bad Mergentheim
Germany
Construction Work
Demolition of the Existing B43 Structure Over the Railroad Tracks:
Scope and Special Features
- The demolition of the existing structure will take place in two construction phases, each involving a complete closure of the railway lines passing underneath
- The bridge superstructure was cut into 20 individual segments using sawing techniques and subsequently removed using cranes. The heaviest segment weighed 190 metric tons, and the lightest weighed 70 metric tons.
- A major challenge is the limited range of motion for the large cranes due to adjacent railroad tracks
- Work is being carried out in multiple shifts