BAB7 Thulba Viaduct, Oberthulba

Construction period

8 months

Client

Adam Hornig Baugesellschaft mbH & Co. KG
Magnolienweg 5 
63741 Aschaffenburg 
Deutschland

Construction Projects

Demolition of the viaduct on the A7 between Fulda and Würzburg

Scope and Special Features

  • Reinforcement of the existing superstructure to accommodate the use of strand-lifting technology
  • Lowering of 5 bridge spans into the valley, each weighing up to 2,000 metric tons
  • Demolition of the 2 end spans, including their respective pairs of piers, by pushing them out from the abutments
  • Directional blasting of the 4 pairs of piers, up to 60 m in height
  • Demolition and recycling of the steel-concrete composite superstructure and all foundation components
  • Recycling of approximately 25,000 metric tons of concrete rubble as a substitute building material in the new construction through crushing and screening