BAB6, BW745B Bridge, Ansbach

Construction period

2 weeks per construction phase

Client

Leonhard Weiss GmbH & Co. KG
Leonhard-Weiss-Straße 2-3
74589 Satteldorf
Germany

Construction Projects

Replacement of the BW745b Bridge on the BAB 6

Scope and Special Features

  • Traffic flow on the A6 must be maintained at all times
  • Work to be carried out in two construction phases, on the lanes heading toward Nuremberg and Heilbronn.
  • Division of the superstructure into 8 segments per direction of travel; excavation using a crawler crane
  • Subsequent excavation of the piers, weighing up to 200 metric tons, using a wire saw and a crawler crane 
  • Demolition of 3,400 m³ of concrete in 2 construction phases 