BAB6, BW745B Bridge, Ansbach
Construction period
2 weeks per construction phase
Client
Leonhard Weiss GmbH & Co. KG
Leonhard-Weiss-Straße 2-3
74589 Satteldorf
Germany
Leonhard-Weiss-Straße 2-3
74589 Satteldorf
Germany
Construction Projects
Replacement of the BW745b Bridge on the BAB 6
Scope and Special Features
- Traffic flow on the A6 must be maintained at all times
- Work to be carried out in two construction phases, on the lanes heading toward Nuremberg and Heilbronn.
- Division of the superstructure into 8 segments per direction of travel; excavation using a crawler crane
- Subsequent excavation of the piers, weighing up to 200 metric tons, using a wire saw and a crawler crane
- Demolition of 3,400 m³ of concrete in 2 construction phases