Demolition of the Heilbronn Neckar Valley Crossing

Construction period

March 2017 through August 2022

A6 West Construction Section: Brief Description

  • 5 overpasses
  • 3 underpasses, approx.
  • 5 km of noise barriers 320,000 metric tons of reinforced concrete 22,000 metric tons of steel

Special Features

  • Demolition of a steel bridge (3,000 metric tons) over the Neckar River using wire rope techniques and floating platforms (pontoons)
  • Blasting demolition of a reinforced concrete bridge; conventional demolition using a cable excavator; segment-by-segment
  • Excavation of bridge sections across the railroad tracks using a large crawler crane
  • Demolition of bridge structures on the public transportation network (complete closure of the A6 / federal and county roads)
  • Demolition within a limited time window
  • Recycling: Crushing and processing of reinforced concrete to a particle size of 0/45 and removal of recycled material
  • Recycling rate of 99%