BAB3 / BAB67 Connecting Ramp at the Mönchhof Interchange in Raunheim
Construction period
Client
Construction Work
Demolition of the old connecting ramp over the A3 and A67 near Frankfurt am Main
Scope and Special Features
- Comprehensive services ranging from project management to planning and execution
- Lifting the 104-meter-long bridge superstructure, weighing approximately 3,200 metric tons, by 5.2 meters
- Construction of a support structure and a temporary bridge
- Demolition on a support structure weighing over 1,000 metric tons
- The demolition of the cantilever elements was carried out using precise sawing techniques
- Work was carried out without disrupting traffic on the A3 and A67